Sitemap |

 
TECHNICAL INFRASTRUCTURE
Người đăng tin: Test Test Ngày đăng tin: 19/10/2017 Lượt xem: 137

 
1. The transportation system
The roads in Danang Hi-Tech Park include:
- The center route with cross-section width: Bn = 51m
- The subdivision routes with cross-section width: Bn = 22.5 m ÷ 33m
- The internal roads in each functional area with cross-section width: Bn = 8m ÷15m.
The roads are connected in chessboard arrangement, convenient for transportation in the Park.

 

2. Waste water treatment plant

- Total capacity: 18.000 m3/day, including 4 modules, each with the capacity of 4.500 m3/day.

- Wastewater from projects must reach class B before entering the Waste water treatment plant.

 
3. Water supply system
The capacity is 10.000 m3/day.
 
4. Power supply system
Danang Hi-Tech Park’s electricity is planned to be supplied by a 110/22KV station with a capacity of 2x63MVA which will be built in Hoa Lien. It is expected that by 2015 one 63MVA transformer will be put into operation ahead. The 110kV double circuit line power station will be connected to the 110kV line from Hoa Khanh to Hai Van Tunnel.
 
Currently, the 110 kV substation with the capacity of 40MVA has started operation.
 
5. Communications system
The underground optical cable system from the city center to DHTP has been constructed.
 
6. Fire prevention system
The D100mm fire hydrants are located along the main pipelines, with a maximum distance of 150m, located at the forks and intersections in DHTP for convenient access to water in case of emergency.
Chuyên mục, tin tức liên quan:

Copyright © 2017 Danang Hi-Tech Park Management Board

Address: Lot C2, Road No.5, Danang Hi-tech park (Km 18, Hai Van Pass - Tuy Loan Road, Hoa Lien Commune, Hoa Vang District, Da Nang City, VietNam)

Tel: +84 236 3566703 - Fax: +84 236 3566705

Email: dhtp@danang.gov.vn

Please cite "Danang Hi-tech Park Website" or "www.dhtp.gov.vn" when quoting information from this Website.